Contact Information
Public Works
208-359-3020
Email Public Works
Featured Construction Updates
Below are the City of Rexburg's 2024 construction season plans for the upcoming months.
Please plan accordingly for possible congestion, detours, or delays in traffic in these areas during construction.
The following projects have tentative start dates. Project length is dependent on several factors as 3rd party contractors are working on these projects. Please note that contractors operate on their own timelines so things may happen faster or slower than anticipated.
UPDATE 9/10/2024: 2nd E from Main St to 1st S closure
Construction has been completed and this block of road has been fully reopened!
2nd E from Main St to 1st S (the block next to Walgreens) will be closed starting this morning. Crews will be replacing the sidewalk, curb and gutter, and sewer lines. They are anticipating paving to begin in about 4 weeks. The block will remain closed to through traffic for the duration of the project. Residents immediately affected should retain access as much as possible.
UPDATE: 7/10/2024: LID 53 – Barney Dairy, 4th East, and North Hill Roads
Barney Dairy Road from 3rd E. to N. Hill Rd. is currently closed to all traffic until approx. Tuesday, July 23rd.
N. Hill Rd. from Barney Dairy Rd. to Nina Dr. is closed for utility installations and resurfacing.
Once Barney Dairy Rd. is complete 4th E. from E. Main St. to 1st N. will be closed for approx. 4 days.
Then work will begin on N. Hill Rd. from N. Millhollow Rd. to Barney Dairy Rd., which will continue for approx. 1 week during which it will be closed to all but local traffic.
Work on 2nd E. from E. Main St. to 1st S. will begin after N. Hill Rd. is completed.
UPDATE 6/11/2024: 2024 CRABS project on University Blvd., Pioneer Rd., and S. Yellowstone Hwy.
Completed!
UPDATE 6/11/2024: Trejo/S. Yellowstone Hwy Traffic Signal Improvements
Underground work is currently taking place.
UPDATE 9/10/2024: Temple Project: Includes 2nd E, north of Moody Rd.
This multi-year project will include intermittent infrastructure updates. Please be vigilant while driving through the area as traffic diversions may be in effect and workers may be present. Thank you!
The project is still underway with utility and other construction happening. Drivers need to be aware of trucks entering and leaving N. 2nd E. in the area.
UPDATE 6/11/2024: Contractors are moving some of the final power poles. Once complete, the road is scheduled to be fully open by Wednesday, June 12th in the evening.
2024 Street Painting: Crews are working on various street painting projects around Rexburg. Progress and affected areas are dependent on weather conditions.
2024 Slurry Seal project is slated to begin in July, following the start of BYUI's 7-week break.
There are no known start dates for the following projects. but they are slated for the 2024 construction season. Work may be done by various entities from City staff to 3rd party bid-and-approved contractors.
Sunrise Sewer Project: The project consists of the construction of a new sanitary sewer mainline from Sunrise Drive to University Blvd. The project will include all the typical road and native ground repairs necessary to install a new gravity sewer with manholes.
7/10/2024: This project has been awarded and is planned to begin in late August.
6/11/2024: Bids have been collected for this project, but it has not been awarded to a contractor at this time.
PLEASE NOTE: This is not an all-inclusive list of projects that may occur in Rexburg for the 2024 season. Other infrastructure projects may also create road closures or restrictions. The city will work to keep residents informed via social media, our website, and on-street signage. We appreciate your patience during this very productive construction season.
The City has compiled an informational webpage about the interchanges and other traffic-effecting road construction plans for the summer of 2024. We hope you find it helpful in planning your routes in the coming months!
2024 ITD Interchange Projects
In the Spring of 2024, the Idaho Transportation Department (ITD) will begin work on Rexburg's 3 interchanges along Highway 20. The south and central exits will each be getting Diverging Diamond Interchanges (DDIs) while the North interchange will be receiving a permanent light signal. Work on the DDI projects will begin in March and is anticipated to last through October. Each of the two interchanges is slated for TWO SEPARATE CLOSURES, each lasting approximately 6 weeks. The first closure is scheduled to begin on the SOUTH INTERCHANGE in mid to late June.
9/10/2024 UPDATE:
Highway 20 Exit 333 will re-open Thursday, 9/12/2024, at night with a new diverging diamond interchange in place. This exit has been closed since late July so the Idaho Transportation Department and contractors could construct the new road design and complete vital underground infrastructure work. The re-opening comes in time for an increase of traffic as university students arrive in Rexburg for the fall semester. All lanes of traffic will be open and construction efforts remain off the roadway at both Exit 332 (University Boulevard) and Exit 333 (Main Street) through [move-in] weekend to accommodate this influx.
Motorists and citizens should be aware that construction efforts will continue again next week and through the month of October. Intermittent single-lane closures will be in place, with traffic still able to move through the interchanges. Impacts will be noted on 511.idaho.gov.
The University Boulevard Exit will fully close again during the week of September 30 through October 4 to allow crews to add a final layer of pavement. This timeframe has been selected in coordination with when Madison School District is out of school for harvest break. Work on both exits is on track to be completed late this Fall. For further details about this project and to watch a video on how to drive the new diverging diamond traffic pattern, visit itdprojects.idaho.gov/pages/us20rexburg.
7/18/2024 UPDATE:
Exit 333 (the Central Exit) has been rescheduled to close a week in advance of it's initial proposed closure date. The exit will now close on Monday, 7/22/2024 for a planned 6-week full closure.
Press release from ITD reads: "The Main Street Exit for Rexburg on U.S. Highway 20 will fully close beginning next Monday. The closure at Exit 333 will allow the Idaho Transportation Department to efficiently construct a diverging diamond interchange (DDI) like the one now operating at University Boulevard (Exit 332). The closure is expected to last through the month of August.
All ramps at Exit 333, as well as Main Street between the ramps, will be closed to traffic and detoured to nearby interchanges. Through traffic on US-20 will be unaffected during construction.
Detours include Thornton (Exit 328), University Boulevard (Exit 332), and North Rexburg (Exit 337). A new permanent traffic signal will be in place and operating to aid the flow of traffic at the North Rexburg Exit prior to this closure. One-lane closures are in effect at the University Boulevard Exit while construction efforts continue there."
7/3/2024 UPDATE:
Exit 332 (the South exit) is back OPEN! Workers will continue to be present at the interchange as there is still much construction to do. The traffic signal that will direct the diverging diamond flow of traffic at this new interchange has been commissioned. Paving is ongoing as they are laying the first “lift” of pavement and a second lift of pavement will still need to be completed after the exit is reopened.
As such, occassional lane closures will still need to happen around the Exit 332 interchange throughout the rest of the summer. One lane of traffic in each direction will stay open even during these times.
** Drivers should familiarize themselves with Diverging Diamond Interchange procedures post-haste! See information on this page below, and on our DDI page.
Exit 333 (the Central exit) is expected to close on July 29th, 2024 for its own 6 week construction period; we hope it will be reopen by Labor Day weekend. Estimated completion of both interchanges (meaning no workers on site) is October, 2024.
6/11/2024 UPDATE:
Work is moving along steadily on the South Rexburg interchange and ITD hopes to have the interchange open by the end of the month. Follow us on social media to be sure you have all the necessary information about how to use DDI's as they will soon be in regular use here in Rexburg!
Prep-work on the central interchange is starting to take place and traffic may be reduced to one lane in each direction intermittently. Full closure of this interchange is expected to take place in July.
5/23/2024 UPDATE:
ITD has announced the closure of the South Rexburg interchange will begin on 5/29/2024! The full closure will be in effect for one month. The interchange is expected to reopen by the Fourth of July. Traffic will be diverted to the Tereton or Central Interchanges, but be advised that active construction has begun on the Central Interchange; plan for delays. See our Diverging Diamond Interchange page for additional information.
How do DDIs work?
This video describes why DDIs were planned for Rexburg interchanges, what a DDI is, and how they work. (Skip to 1:14 for a helpful instructional animation.)
Preparation for the new Rexburg LDS Temple
With the announcement of a new LDS Temple going in on the North end of 2nd E (through Moody Rd), many infrastructure improvements have been slated for the summer along that route that will be affecting traffic on that road. Projects include:
Sewer & water upgrades
Widening of 2nd E to a 5-lane road
Signal upgrade at the North HWY 20 interchange
Curb and gutter upgrades
Work has already begun in this area and is expected to last throughout the entire summer.